Ask how the operating carrier is implementing safety management—not whether the broker has purchased SMS software. The expanded Part 5 framework requires affected operators to develop and implement a safety management system and, where the transitional provisions apply, submit a declaration of compliance by 28 May 2027. (ecfr.gov)
The final rule was published on 26 April 2024 and became effective on 28 May 2024. Its practical relevance in current procurement is the approaching implementation deadline, rather than a newly announced October 2026 rule. (faa.gov)
Does every operator have until May 2027?
No. FAA’s implementation table distinguishes existing certificate holders from new applicants and transitional applicant categories. Operators certificated before 28 May 2024 have the stated May 2027 deadline; many new applicants must implement SMS upon certification, with specific transitional treatment for certain applications. Ask the carrier to identify the category applicable to its certificate. (faa.gov)
Nor should buyers assume that every ordinary Part 91 flight department or Part 91 Subpart K fractional programme has acquired the same mandatory deadline. FAA’s implementation FAQ identifies Subpart K among eligible voluntary-programme participants. (faa.gov)
What should procurement ask for now?
Request a short, signed response covering:
- Applicability: Which Part 5 requirements and implementation dates apply to this operating entity?
- Accountability: Who owns implementation, and who escalates unresolved safety concerns?
- Progress: What is operational now, what remains incomplete, and when will outstanding work finish?
- Evidence: Can the carrier provide a non-sensitive example of hazard reporting, risk assessment and follow-up?
- Assurance: How will it test whether its controls work after implementation?
- Buyer notification: Will it notify the customer if a regulatory issue materially affects delivery?
These questions reflect the FAA’s four SMS components: safety policy, safety risk management, safety assurance and safety promotion. They are buyer-selected evidence requests, not a replacement for FAA oversight. (faa.gov)
Do not invent a separate Part 135 implementation-plan filing deadline. The final rule distinguishes the declaration-of-compliance approach for Part 135 operators from the implementation-plan submission requirements for affected design and manufacturing organisations. A buyer can request milestones commercially without calling them a separate statutory filing obligation. (faa.gov)
Does an IS-BAO registration settle the question?
Treat an industry standard and regulatory compliance as separate evidence categories. IBAC describes IS-BAO as its business-aircraft operations safety standard with an audit and registration process; the FAA’s Part 5 obligations remain a distinct requirement where applicable. Ask the supplier to map its existing programme to the applicable rule rather than accepting a logo as the entire answer. (ibac.org)
No specific new 2026 IS-BAO standards amendment is asserted here: a sufficiently detailed public change log was not established in this research.